Water managers at the U.S. Army Corps of Engineers, along with federal, tribal, and state fish biologists, determined forecasted inflows are sufficient to provide flow augmentation at Libby Dam, Mont., for endangered Kootenai River white sturgeon downstream in Idaho.

While this year’s flow augmentation for sturgeon does not include spilling additional volume from the dam, plans include increasing flows to full powerhouse capacity for about a week, on two separate occasions, in an effort to provide river conditions that may foster sturgeon spawning.

Sturgeon flow augmentation will begin Friday when local Kootenai River tributaries downstream of Libby Dam are forecasted to peak, the trigger for initiating releases from the dam in support of sturgeon spawning activity.  Flows will be increased to full powerhouse capacity, approximately 24,500 cubic feet per second, and will remain at that level for about one week before decreasing to 18,000 cfs. 

A second week-long pulse of powerhouse capacity flows is expected to start at the end of May to coincide near peak inflows above the dam.

The sturgeon flow augmentation operation is part of a collaborative, ongoing effort by regional biologists to enhance spawning and migration conditions for sturgeon in the Kootenai River near Bonners Ferry, Idaho.  Increased flows are intended to provide river conditions that may increase sturgeon migration to the reach of river upstream of Bonners Ferry in habitat thought to be conducive to successful spawning, egg hatching, and survival of larval sturgeon While the Kootenai Tribe of Idaho’s conservation aquaculture program has steadily increased the number of young sturgeon in the river since 1992, federal, state, and tribal partners have collaborated in recent years to construct instream habitat upstream of Bonners Ferry intended to provide conditions that will allow adult sturgeon to successfully reproduce on their own. 

The sturgeon operation requires a volume of water to be released from Libby Dam based on the May water supply forecast.  The May water supply forecast for the April to August inflow volume is 7.0 million-acre-feet, or 119 percent of average; which sets this year’s sturgeon volume at 1.17 million-acre-feet. 

While snowpack has begun to melt in western Montana and northern Idaho, cooler temperatures and early precipitation in May have maintained the snowpack in the upper Kootenai Basin above Libby Dam. 

The latest projections indicate a 17 percent chance of exceeding flood stage at Bonner Ferry, Idaho, which is 1,764 feet.  Although June precipitation may increase flood risk from downstream tributaries to the Kootenai River which are not controlled by the dam, flood risk decreased from April’s projections due to increased certainty in Kootenay Lake elevations for the month of May.

Libby Dam flow and stage projections are based on National Weather Service ensemble forecasts and are updated frequently during runoff season as weather and conditions change.  Forecast modeling includes information on elevations, outflow, and Bonners Ferry seasonal elevation and peak height for the year.  To see the latest projections, visit: http://1.usa.gov/1kP1lSH.

The U.S. Army Corps of Engineers' primary consideration in operating Libby Dam is to minimize risk to human life, health, and safety, while meeting the dam’s multiple purposes and responsibilities. The Corps will closely monitor Kootenai River elevation in Bonners Ferry during the sturgeon flow augmentation and will adjust operations with the aim of staying below 1,764 feet, the local flood stage.

Public information meetings for Libby Dam operations are scheduled for:

·         May 29 at the Kootenai River Inn, Bonners Ferry, Idaho, from 6-8 p.m.
·         June 9 at Lincoln Electric Cooperative, Eureka, Mont., from 6-8 p.m.
·         June 11 at Lincoln County Credit Union, Libby, Mont., from 7-9 p.m.


Release no. 14-021