Public Meetings

Spring 2024

Thursday, May 30, 6:00 p.m. - 8:00 p.m. at Ponderay Events Center, 401 Bonner Mall Way, Suite E, Ponderay, ID 83852

Friday, May 31, 9:00 a.m. - 11:00 a.m., Camas Center for Community Wellness, 1821 N. LeClerc Rd. #5, Cusick, WA 98119
 
 

Fall 2024

Monday, Oct. 7, 6:00 p.m. - 8:00 p.m. at Ponderay Events Center, 401 Bonner Mall Way, Suite E, Ponderay, ID 83852

Albeni Falls Dam Spillway Gate Replacement Project Fall 2024 Presentation 

 

Spring 2025 

Thursday, May 1, 6:00 p.m. - 8:00 p.m. at Ponderay Events Center, 401 Bonner Mall Way, Suite E, Ponderay, ID 83852

Friday, May 2, 9:00 a.m. - 11:00 a.m., Camas Center for Community Wellness, 1821 N. LeClerc Rd. #5, Cusick, WA 98119

Press Releases for Albeni Falls Dam

 

FAQs

Spillway Gates Replacement Project Industry Day (Jan 29-30, 2025) Documents 

Contract Opportunity General Information (SAM.gov)

 

Spillway Gate Defects & Flaws

Photo of one of the spillway gates in operation at Albeni Falls Dam, Oldtown, Idaho. Photo shows the upper and lower leaves and girders that are critical components of a spillway gate.
Photo of delamination on steel girder
Photo of delamination on steel girder
Photo of delamination on steel girder

Spillway Gate Defects Background

In June 2023, the Army Corps of Engineers began physical work on a gate rehabilitation contract, which was to repair cracked welds identified during routine gate inspections and to re-paint the gate.

As part of this rehabilitation contract, gate 3 was removed and the spare gate was put in its place.

The paint on gate 3 was removed and an in-depth gate inspection was completed. 

During the gate rehabilitation, steel defects were discovered in critical girders in April 2024.

These base metal defects include holes and cracks in the steel. In the event a gate should fail, it could lead to injury to the crane operator, damage to the crane and bridge, and loss of control of lake level. 

Spillway Gate Defects Observations and Implications

The current defects were likely a result of the steel rolling process that was used in the 1950s. The rolled steel has likely worsened over time.

All spillway gates and the spillway bridge were built at the same time (1950s) with the same steel fabrication (Federal Specification QQ-S-741a or ASTM A7 Steel).

The only way the current defects could have been effectively discovered and identified was after gate 3 was removed from service and its paint removed. 

The current defects can increase/grow through further gate use and subjecting them to load from water pressure. Operating the gates to control water flow creates dynamic loads on the gates, increasing risk/stress on them.

These defects do not pose a safety risk to the public.

Restricted Operations - Water Year 2025

Safety of our dam operators and maintaining our routine operations is paramount. As a result of these defects, in May 2024 we restricted operations. 

For the 2025 water year, restrictions include: 

Minimizing gate movements to minimize the risk of gate failure by operating the gates in either fully open or fully closed positions only.
 
Upstream
  • Goal for intermediate 2060.0 ft. level by late May.
  • Goal for summer pool 2062.0 ft. by June 20.
  • Operate to our normal one-half foot summer range (2062.0 - 2062.5 ft)
  • Subject to change, depending on weather conditions affecting runoff quantity and intensity

Downstream

  • Will most likely look like normal operations.

Operating conservatively today reduces the risk of a catastrophic failure of any gate. 

In the event of a gate failure, several impact scenarios exist depending on multiple factors such as how the failure occurs and the time of year. 

  • Implications of a gate failure to upstream residents could result in a SLOW loss of lake level below an elevation of 2051 ft.
  • Implications of a gate failure to downstream residents would NOT result in flooding as the river channel capacity can absorb the inflow in the event of a sudden, uncontrolled release of water. 

Regardless of the scenario, failure of a spillway gate would impact the project's ability to maintain stable lake levels. 

Long-Term Planning

  • The Army Corps is working toward a temporary repair to gate 3, allowing the project to have its one backup gate. Restricted operations will remain in place. ​​

  • Funding for the new spillway gate/s design has been secured. Design is making great progress and expected to be complete July 2025, two months earlier than originally anticipated.​​

  • Anticipate advertising contract for new gates late 2025. The first gate would arrive onsite in 2027 and subsequent gates arriving in 6-month intervals, dependent on industry capability at the time. Confirmed timeline during Industry Day in late January with interested contractors.

Water Management

Let Us Know!

We understand the importance of Lake Pend Oreille to the community and lake users.

While we continue our restricted operations to ensure we're operating in a safe and reliable manner, we realize the effect they have had on residents' access to recreational opportunities and on the economy in North Idaho in general. 

Let us know how these restrictions have affected you, by emailing us at: AFDpublicinput@usace.army.mil

Help Us Improve Our Website!

We're looking to enhance our website to better serve you.

Your feedback is crucial in helping us make the right improvements, and we would greatly appreciate your input.

Send your suggestions to: nicole.l.celestine@usace.army.mil