In June 2023, the Army Corps of Engineers began physical work on a gate rehabilitation contract, which was to repair cracked welds identified during routine gate inspections and to re-paint the gate.
As part of this rehabilitation contract, gate 3 was removed and the spare gate was put in its place.
The paint on gate 3 was removed and an in-depth gate inspection was completed.
During the gate rehabilitation, steel defects were discovered in critical girders in April 2024.
These base metal defects include holes and cracks in the steel. In the event a gate should fail, it could lead to injury to the crane operator, damage to the crane and bridge, and loss of control of lake level.