Large Lock center gate extended closures schedule:
Closure #1 : 10/16/2023 - 11/14/2023
Single Chamber Navigation: 11/15/2023 -11/29/2023
Closure #2: 11/30/2023 - 12/29/2023
Single Chamber Navigation: 12/30/2023 1/13/2024
Optional Closure: 1/14/2024 - 2/12/2024
Single Chamber Navigation: 2/13/2024 -10/14/2024
Closure #3: 10/15/2024 - 11/13/2024
Single Chamber Navigation: 11/14/2024 - 11/28/2024
Optional Closure: 11/29/2024 - 12/28/2024
Fully Operational: 12/29/2024
Please note:
- For each closure cycle, the Large Lock will close for no more than 30 days and open for 15 days for vessel traffic.
- Closure windows are projected and may change as the Contractor's project schedule is finalized.